War Memorial Stadium/Jonah Field Preparation - Photo Gallery

Share:
Football 7/5/2005 2:00:00 AM

July 5, 2005

LARAMIE, Wyo. -

The project remains on schedule. The new goal posts have been installed and painted. The contractor is completing installation of the underground drain piping, and is spreading a crushed rock field base. Two new entrances to the stadium have been poured on the east side. South endzone bleachers are being removed and the new turf has started to be delivered in rolls.